Phu Lac wind power plant switches on

16/11/2016 12:11

The Phu Lac wind power plant located in the Tuy Phong district, central coastal Binh Thuan province, will be completed on November 25 after 14 months of construction.

 The project has a total investment of nearly 1.1 trillion VND (49.3 million USD), including 85 percent of loans from the German Development Bank (KfW).

In September, the plant successfully put its first turbine into operation and connected with the national power grid. The Phu Lac Wind Power Plant, in its first phase, has a total capacity of 24MW which uses the technology of Denmark-based Vestas brand with 12 piers.
 
After going through Phu Lac transformer station, the power source was officially connected with the 110KV Ninh Phuoc-Tuy Phong transmission line of the national power grid, supplying additional power for Binh Thuan province and the southern provinces.
 
Source: VNA